RIETVLEI AND EMBUZWENI WATER SUPPLY – PHASE 1 AND 2

The Client, the Sisonke District Municipality, appointed Scientific Roets (PTY) Ltd to design and manage the development of a water reticulation service in the areas of Rietvlei and Embuzweni.
PHASE 1- RESERVOIRS, BOREHOLES, A PUMPSTATION AND BULKLINE
Two boreholes will be developed to supply water to the villages of Rietvlei and Embuzweni. A pumpstation with two positive displacement pumps as well as a standby generator will be constructed to pump the water to a new concrete reservoir - 400m3 in size - that will be constructed above the Rietvlei village. A rising 63-110mm uPVC pipeline will inter-connect the boreholes, pump station and the 400m3 reservoir. The water will also gravitate through a 90mm uPVC pipeline to a new 120m3 concrete reservoir to supply Embuzweni village. This project also includes the construction of air valves, scour valves and valve chambers.
Progress to date includes the cutting of the platforms for the reservoirs and pump station and approximately one kilometer of pipeline trench has been excavated.



Excavation of the trench for the pipeline


PHASE 2- WATER RETICULATION FOR RIETVLEI AND EMBUZWENI
Phase 2 is the water reticulation phase of this water supply project. It is made up of approximately 13Km of 32- 75mm uPVC and HDPE reticulation pipelines, 45 standpipes, valve chambers and fittings.
This phase of the project has passed the tender stage. Tender adjudication has been done and we are waiting for the appointment of a contractor in order for the construction stage to begin.