Our BEE Scorecard

Our Grand Opening

Our New Offices

Projects

 

 
Kokstad Landfill Site

This project, in service to the Greater Kokstad Municipality, was aimed at rehabilitating the Kokstad Landfill Site into a more convenient dumping area, to control the way people were dumping and also to relocate people who were living on the dumping site. This project was divided into two contracts. i.e. Fence Contract and Earthworks Contract



1. Fence Contract

Fencing the area served to control and prevent unauthorized entry onto the dumping site premises. This contract took three months to complete. Fencing has ensured that there is no further unauthorized entry; all the people entering the site now leaves their details at the gate.

2. Earthworks Contract

This contract consisted of several activities:
• Dividing the dumping site into cells so that there will be an organized process of dumping.
• Installation of a sub-soil drainage system because the dumping area is situated on a wetland (the sub-soil drainage pipe channels water into a pond which is situated at the lower level of the dumping area).
• Excavating two ponds to store water coming from the dumping area.
• Construction of a retaining wall outside the dumping site which will be used for separating the garbage e.g. bottles, papers, metal etc.