Our BEE Scorecard

Our Grand Opening

Our New Offices

Projects

 

 

KWAXOLO CHICKEN PROJECT

OVERVIEW



An investigation into the potential feasibility of a Chicken Production and Processing Facility in the KwaXolo area of the Hibiscus Coast Municipality was requested by the Hibiscus Coast Municipality in 2005. Scientific Roets (PTY) Ltd was appointed to assess this feasibility and the KwaXolo Chickens Feasibility Study and Business Plan was developed. Funding was sought to implement the business during 2006. R 4.2 million was obtained from the EU Gijima Fund, R 1 million was obtained from the Hibiscus Coast Municipality and R 2.4 million was obtained from the Dept. of Local Government and Traditional Affairs.

PROPOSED PROJECT AND BUSINESS ORGANISATION

KwaXolo Chickens will be operated as an integration. This entails that the central abattoir facility (a farmer’s co-operative) will contract in excess of 20 broiler producer groups (also registered as farmer’s co-operatives or trusts) to grow broilers on a pre-determined production schedule. The central facility will manage the ordering and delivery of day-old chicks, bedding material, feed and medicine to the broiler producers. These costs will then be deducted from the bill paid to each broiler producer group on delivery of their birds.
Utilising the scenarios recommended by the Business Plan KwaXolo Chickens can provide permanent employment opportunities for approximately 243 individuals. During the construction phase approximately 100 temporary employment opportunities are being created.



PROGRESS

Training:

Funding was obtained from AgriSETA to conduct a Poultry Production Skills Programme. Thirty learners were nominated from within the poultry production groups identified by the Business Plan. This training was completed in March 2007. Further funding for a full NQF 1: Poultry Production Learnership for 120 of the KwaXolo Chicken Producers has been obtained from AgriSETA for 2008 and 2009. This training will commence in February 2008.

Improved production infrastructure for Co-operatives:

Funding applications to upgrade the production facilities have been submitted to various donor and government agencies.

Central Facility Abattoir:

The Central Facility Infrastructure was designed, the EIA Record of Decision obtained and ESKOM Power lines across the property were diverted. A sod-turning Ceremony was held on the site and construction was begun. The first phase of construction consists of the construction of platforms, cut to fill 3600m3, subsoil drainage, SBS reservoir, concrete chambers, two boreholes and interconnecting pipe work. Connection at Eskom is also required along with a standby generator 50 kVA, cabling of approximately 350m, mortality pits and sludge disposal. To date, this phase is at 98% completion.

Project manager, client and donor representatives in front of the mortality pits
Phase 2, which will consist of the construction of the top-structure (administration buildings, security building, ablution facilities, lunch room and abattoir), has passed the tender stage. The tender adjudication has been done and we are waiting for the appointment of the contractor. When the contractor has been appointed, the construction stage will begin.

Institutional arrangements:

Two meetings have been conducted to inform and guide beneficiaries regarding the organisational arrangements of the KwaXolo Chicken Enterprise. These activities are on-going and will be further emphasised during 2008 in conjunction with the NQF 1: Poultry Production Learnership.